If you are fully or partially demolishing a structure contact the Building Division at buildingpermits@cityssm.on.ca or 705-759-5410 for more information.
A demolition permit is required before you take down all or part of a building.
The process is much the same as for a building permit; however, your application may be affected by special situations. For example, if a building has historical or architectural significance, it may be designated as a heritage building under the Ontario Heritage Act and require approval from the Sault Ste. Marie Municipal Heritage Committee will be required. In some cases, you must hire a professional engineer to oversee the demolition.
To apply for a demolition permit, you must complete the Application for a Permit to Construct or Demolish and the Demolition Permit Utility Notification. A pest control report from a local pest control company is also required. These documents must be provided at the time of application.