Queen Street is the heartbeat of Sault Ste. Marie. It’s a destination for entertainment, culture, and retail activities. Recent successes like the Downtown Plaza and Soo Market have showcased its potential.
Contact Information
AECOM Canada will oversee the construction on behalf of the City and will have staff on-site full-time. If you have any questions or concerns relating to the project, contact an AECOM representative below:
AECOM Representatives
City Staff Contact
Maggie Mcauley
Manager of Design and Transportation Engineering
705-759-5385
m.mcauley@cityssm.on.ca
Tessa Vecchio
Corporate Communications
705-759-5396
t.vecchio@cityssm.on.ca
Project Updates
Detour for ES, GNR, RM (Inbound only)

2025 Progress
Queen Street Improvements: September 22-26, 2025
Progress
During the last week, the Contractor has undertaken the following activities:
Elgin to East
- Completed final pavement markings on surface asphalt throughout limits.
Brock to East
- Completed installation of unit pavers in boulevard on south side and some jointing sand.
- Completed tree grates and planter in south boulevard.
- Removed temporary fencing and started cleaning up site.
Proposed Activities
This week the Contractor is proposing to undertake the following this week:
Elgin to Brock
- Complete deficiencies.
Brock to East
- Complete boulevard restoration on Brock.
- Complete jointing sand in unit paver boulevard.
- Plant remaining trees (subject to receipt from supplier).
- Install remaining furnishings
- Install remaining banner arms on light poles.
- Remove traffic control barrels and reopen Queen to two-lanes.
- Complete final clean-up and demobilize from the site.
Impacts
Queen Street will be fully reopened to two lanes of traffic by Friday, September 26.
Minor construction activities may continue beyond this week, such as tree planting and banner arm installation, which could require brief, localized lane closures during daytime hours.
City crews will be on site over the coming weeks to complete pavement marking symbols and installation of signage, bus shelters, pay-and-display parking units and other related work.
Schedule
- Elgin to Spring – All work is now completed.
- Spring to Brock – All work is now completed.
- Brock to East – The remaining work is scheduled to be completed this week with only minor items to be done after this week.
On behalf of the City, we sincerely thank all adjacent business owners and residents for their patience and cooperation throughout the Queen Street Improvements project. We hope you are pleased with the final result, which we believe will have a positive impact on the downtown area.
Queen Street Improvements: September 15-19, 2025
Progress
During the last week, the Contractor has undertaken the following activities:
Brock to East
- Continued with installation of unit pavers in boulevard on south side.
- Installed tree grates and installation of last planter in south boulevard.
- Completed final paving of Queen Street and parking bays on both sides of Queen.
- Completed some line painting on surface asphalt.
Proposed Activities
This week the Contractor is proposing to undertake the following activities:
Elgin to Brock
- Place pavement markings and lines on surface asphalt.
Brock to East
- Complete installation of unit pavers in south boulevard, pending weather conditions.
- Complete tree grates and planter in south boulevard.
- Place pavement markings and lines on surface asphalt.
Impacts
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of July 2nd, the south lane is closed between Brock and East with traffic diverted to the north lane. Queen Street will be closed between Brock Street and Spring Street and between Spring Street and March Street from 6:00 p.m. Monday, September 15th to 7:00 a.m. Tuesday, September 16th. The closure is necessary to allow line painting to be done in this area.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Concrete sidewalk is complete on both sides and remaining work is limited to the south boulevard which is fenced off from the sidewalk until completion.
Schedule
- Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings is completed except for some minor items.
- Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings is completed except for a few minor items.
- Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. All asphalt paving work is now completed and the remaining work in the south boulevard is expected to be completed over the next 2 weeks.
We understand that the construction may cause some inconvenience to the adjacent business and property owners, but every effort will be made to minimize the disruptions, where possible.
Queen Street Improvements: September 8-12, 2025
Notice: Temporary Road Closure – Queen Street from East Street to Brock Street
Queen Street will be fully closed between East Street and Brock Street for 1 day on Monday, September 8. The closure is necessary to allow placement of the final asphalt surface course as the wet weather prevented completion this past week.
Progress
During the last week, the Contractor has undertaken the following activities:
- Brock to East (north side)
- No work done.
- Completed placement of asphalt in boulevard at East Street.
- Brock to East (south side)
- Continued with installation of unit pavers in boulevard.
- Installed sign posts.
- Installed new street light poles.
- Completed placement of asphalt in boulevard at East Street.
- Placed 2nd lift of asphalt binder course in roadway and raised manholes in preparation for final lift.
Proposed Activities
This week the Contractor is proposing to undertake the following activities:
- Brock to East (north side)
- Place final lift of asphalt surface course in parking bays (September 8th).
- Place final lift of asphalt surface course within roadway.
- Brock to East (south side)
- Continue with installation of unit pavers in boulevard.
- Place final lift of asphalt surface course in parking bays (September 8th).
- Place final lift of asphalt surface course within roadway.
Impacts
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of July 2nd, the south lane is closed between Brock and East with traffic diverted to the north lane. Queen Street will be fully closed between East Street and Brock Street for 1 day on Monday, September 8th. The closure is necessary to allow placement of the final asphalt surface course as the wet weather prevented completion this past week.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Concrete sidewalk is complete on north side and work has commenced on south side with temporary walkway and fencing being erected throughout limits.
Schedule
- Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings is completed except for some minor items.
- Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings is completed except for a few minor items.
- Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September. The work on north side is completed except for final paving. Work on the south side has commenced as of July 2nd and is progressing well. After the paving work is completed the week of September 2nd, the remaining work will be limited to placement of the unit pavers in the boulevard and placement of furnishings and trees.
We understand that the construction may cause some inconvenience to the adjacent business and property owners, but every effort will be made to minimize the disruptions, where possible.
Queen Street Improvements: September 2-5, 2025
Notice: Temporary Road Closure – Queen Street from East Street to Brock Street
Queen Street will be fully closed between East Street and Brock Street for 1 day on Monday, September 8. The closure is necessary to allow placement of the final asphalt surface course as the wet weather prevented completion this past week.
Progress
During the last week, the Contractor has undertaken the following activities:
- Brock to East (north side)
- No work done.
- Brock to East (south side)
- Grading boulevard in preparation for pavers.
- Commenced with installation of unit pavers in boulevard.
- Installed sign posts.
- Placed 1st lift of asphalt binder course in roadway.
Proposed Activities
This week the Contractor is proposing to undertake the following activities (asphalt paving is weather pending):
- Brock to East (north side)
- Place final lift of asphalt course in parking bays and adjust manholes to grade within roadway (September 3rd).
- Place final lift of asphalt within roadway (September 4th).
- Brock to East (south side)
- Continue with installation of unit pavers in boulevard.
- Place 2nd lift of asphalt binder course in roadway (September 2nd ).
- Place final lift of asphalt course in parking bays and adjust manholes to grade within roadway (September 3rd)
- Install new street light poles (September 3rd).
- Place final lift of asphalt within roadway (September 4th).
Impacts
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of July 2nd, the south lane is closed between Brock and East with traffic diverted to the north lane. Queen Street will be fully closed between East Street and Brock Street for 3 days from Tuesday, September 2nd to Thursday September, 4th. The closure is necessary to complete the final paving work on Queen.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Concrete sidewalk is complete on north side and work has commenced on south side with temporary walkway and fencing being erected throughout limits.
Schedule
- Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings is completed except for some minor items.
- Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings is completed except for a few minor items.
- Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September. The work on north side is completed except for final paving. Work on the south side has commenced as of July 2nd and is progressing well. After the paving work is completed the week of September 2nd, the remaining work will be limited to placement of the unit pavers in the boulevard and placement of furnishings and trees.
We understand that the construction may cause some inconvenience to the adjacent business and property owners, but every effort will be made to minimize the disruptions, where possible.
Queen Street Improvements: August 25-29, 2025
Notice: Temporary Road Closure – Queen Street from East Street to Brock Street
Queen Street from East Street to Brock Street will be closed for three days beginning Tuesday, September 2, 2025. This closure is required to facilitate the final lift of paving in the area.
The sidewalk will remain open. Motorists and pedestrians are advised to be cautious in the area and obey all signage.
The City of Sault Ste. Marie thanks its citizens for their patience and cooperation during this temporary road closure.
Progress
During the last week, the Contractor has undertaken the following activities:
Brock to East (north side)
- No work done.
Brock to East (south side)
- Completed concrete curbs and tree grates.
- Grading boulevard in preparation for pavers.
- Grading and compacting roadway in preparation for asphalt paving.
- Placed asphalt binder course in parking bays.
Proposed Activities
This week the Contractor is proposing to undertake the following activities:
Brock to East (north side)
- No work planned until final paving.
Brock to East (south side)
- Commence with installation of unit pavers in boulevard.
- Install sign posts.
- Place first lift of asphalt binder course in roadway (August 25th).
- Install light poles (week of September 2nd).
Impacts
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of July 2nd, the south lane is closed between Brock and East with traffic diverted to the north lane.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Concrete sidewalk is complete on north side and work has commenced on south side with temporary walkway and fencing being erected throughout limits.
Schedule
- Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings is completed except for some minor items.
- Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings is completed except for a few minor items.
- Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September. The work on north side is completed except for final paving. Work on the south side has commenced as of July 2nd and is progressing well.
Queen Street Improvements: August 18-22, 2025
Brock to East (north side)
- Installed new trees.
Brock to East (south side)
- Poured concrete roadway curb for much of the limits.
Proposed Activities
This week the Contractor is proposing to undertake the following activities:
Brock to East (north side)
- No work planned until final paving.
Brock to East (south side)
- Complete the remaining roadway concrete curb at Brock and tie-ins.
- Grade boulevard in preparation for unit pavers.
- Install concrete collars for tree grates.
- Install light poles.
- Tentatively planning on paving of parking bays.
Impacts
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of July 2nd, the south lane is closed between Brock and East with traffic diverted to the north lane.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Concrete sidewalk is complete on north side and work has commenced on south side with temporary walkway and fencing being erected throughout limits.
Schedule
Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings is completed except for some minor items.
Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings is completed except for a few minor items.
Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September. The work on north side is completed except for final paving. Work on the south side has commenced as of July 2nd and is progressing well.
Queen Street Improvements: August 11-15, 2025
- Replaced unit pavers in front of Cenotaph at Courthouse.
- Installed furnishings.
- Completed general clean-up and removed temporary fencing.
- Poured concrete curb for parking bays and set up for roadway curb.
Brock to East (north side)
- Complete installation of remaining furnishings.
- Complete new concrete curbs for parking bays and roadway.
- Commence with grading boulevard in preparation for unit pavers.
- Install light poles, if timing permits.
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of July 2nd, the south lane is closed between Brock and East with traffic diverted to the north lane.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Concrete sidewalk is complete on north side and work has commenced on south side with temporary walkway and fencing being erected throughout limits.
- Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings is completed except for some minor items.
- Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings is completed except for a few minor items.
- Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September. The work on north side is progressing on schedule. Work on the south side has commenced as of July 2nd.
Queen Street Improvements: August 5-8, 2025
- Replaced unit pavers in front of Cenotaph at Courthouse.
Brock to East (north side)
- Installed furnishings.
- Completed general clean-up and removed temporary fencing.
Brock to East (south side)
- Poured concrete curb for parking bays and set up for roadway curb.
Proposed Activities
Brock to East (north side)
- Complete installation of remaining furnishings.
- Complete new concrete curbs for parking bays and roadway.
- Commence with grading boulevard in preparation for unit pavers.
- Install light poles, if timing permits.
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of July 2nd, the south lane is closed between Brock and East with traffic diverted to the north lane.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Concrete sidewalk is complete on north side and work has commenced on south side with temporary walkway and fencing being erected throughout limits.
- Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings is completed except for some minor items.
- Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings is completed except for a few minor items.
- Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September. The work on north side is progressing on schedule. Work on the south side has commenced as of July 2nd.
Queen Street Improvements: July 28-August 1, 2025
Queen Street Improvements: July 14-18, 2025
Progress
During the last week, the Contractor has undertaken the following activities:
Brock to East (north side)
- Completed grading and placement of bedding sand in boulevard in preparation for pavers.
- Continued with installation of unit pavers in boulevard towards East Street.
Brock to East (south side)
- Completed removal of pavers, concrete curbs and asphalt in parking bays.
- Worked on underground work including replacement of curb stops and installation of catch basin.
- Commenced with construction of tree soil cells.
- De-energized and removed existing street light poles.
Proposed Activities
This week the Contractor is proposing to undertake the following activities:
Spring to Brock
- Place jointing sand in recently installed pavers near Brock.
Brock to East (north side)
- Continue with installation of unit pavers in boulevard area towards East.
- Complete construction of precast block planter wall near Brock.
Brock to East (south side)
- Continue with construction of tree soil cells.
- Work on upgrades of storm sewer including catch basins, drains etc.
- Commence work on electrical ducts for new street lighting.
Impacts
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of July 2nd, the south lane is closed between Brock and East with traffic diverted to the north lane.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Concrete sidewalk is complete on north side and work has commenced on south side with temporary walkway and fencing being erected throughout limits. Temporary closures of sidewalk along the south side will be necessary to complete adjacent underground work. Sidewalk closure signs will be erected.
Schedule
- Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings is completed except for some minor items.
- Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings is completed except for a few minor items.
- Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September. The work on north side is progressing on schedule. Work on the south side has commenced as of July 2nd.
We understand that the construction may cause some inconvenience to the adjacent business and property owners, but every effort will be made to minimize the disruptions, where possible.
Queen Street Improvements: July 7-11, 2025
Spring to Brock
- Reinstalled pavers on south side near Brock.
Brock to East (north side)
- Diverted traffic to the north side as of July 2nd.
- Completed grading and placement of bedding sand in boulevard in preparation for pavers.
- Commenced with installation of unit pavers in boulevard from Brock Street.
Brock to East (south side)
- Worked on removal of pavers.
- Erected temporary fence and walkway in removal areas.
This week the Contractor is proposing to undertake the following activities:
Spring to Brock
- Place jointing sand in recently installed pavers near Brock.
Brock to East (north side)
- Continue with installation of unit pavers in boulevard area towards East.
- Complete construction of precast block planter wall near Brock.
- Brock to East (south side)
- Continue with removals and erection of temporary walkway/fencing.
- Commence with construction of tree soil cells.
- De-energize and remove existing street light poles.
- Commence work on electrical ducts for new street lighting.
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of July 2nd, the south lane is closed between Brock and East with traffic diverted to the north lane.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Concrete sidewalk is complete on north side and work has commenced on south side with temporary walkway and fencing being erected.
- Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings is completed except for some minor items.
- Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings is completed except for a few minor items.
- Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September. The work on north side is progressing on schedule. Work on the south side has commenced as of July 2nd.
Queen Street Improvements: July 1-4, 2025
Progress
During the last week, the Contractor has undertaken the following activities:
Elgin to Spring
- None.
Spring to Brock
- None.
Brock to East (north side)
- Received shipment of unit pavers.
- Completed concrete curbs, collars for tree grates and base for retaining wall.
- Worked on backfilling and grading boulevard areas in preparation for pavers.
- Paved 1st lift of asphalt within parking bays and travel lane along north side.
Proposed Activities
This week the Contractor is proposing to undertake the following activities:
Elgin to Spring
- Complete outstanding deficiencies.
Spring to Brock
- Reinstall pavers on south side near Brock that were installed temporarily until new pavers were received.
Brock to East
- Continue with grading and placement of bedding within north boulevard in preparation for pavers.
- Commence with construction of precast block wall for planter, near Brock.
- Divert traffic to north lane and close south lane on July 2nd.
- Commence with removals and installation of temporary walkway and fencing on south side.
Impacts
Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of May 14th, the south lane is closed between Elgin and Brock and the north lane is closed between Brock and East. The through traffic on Queen Street will be diverted from the south side to the north side as of July 2nd to allow construction work to commence on the south side.
With the concrete sidewalk and most of the work finished between Elgin and Brock, except for the boulevard work between Brock and Spring on the south side, disruptions and access to businesses in these areas should be minimized.
For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Concrete sidewalk now complete on north side.
Schedule
Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings has commenced as of April 21st and is completed except for some minor items.
Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings has commenced as of April 28th and is completed except for a few minor items.
Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September. The work on north side is progressing on schedule. Work on the south side is anticipated to commence late June.
Contractor took Monday, June 30th off and continued with work on site as of Tuesday, July 1st.
Queen Street Improvements: June 23-27, 2025
Progress
During the last week, the Contractor has undertaken the following activities:
Elgin to Spring
None.
Spring to Brock
- None.
Brock to East (north side)
- Completed concrete curbs for parking bays.
- Poured concrete curb along road.
- Worked on backfilling and grading boulevard areas in preparation for pavers.
- Installed street light poles.
Proposed Activities
This week the Contractor is proposing to undertake the following activities:
Elgin to Spring
Complete outstanding deficiencies.
Spring to Brock
- Complete outstanding deficiencies.
Brock to East (north side)
- Complete remaining concrete curb.
- Install tree grates.
- Grade boulevard in preparation for unit pavers to commence next week.
- Place asphalt binder course in parking bays and along north side of Queen between Brock and East.
Impacts
Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of May 14th, the south lane is closed between Elgin and Brock and the north lane is closed between Brock and East. The through traffic on Queen Street will be diverted from the south side to the north side the week of July 1st to allow construction work to commence on the south side.
With the concrete sidewalk and most of the work finished between Elgin and Brock, except for the boulevard work between Brock and Spring on the south side, disruptions and access to businesses in these areas should be minimized.
For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Concrete sidewalk now complete on north side.
Schedule
Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings has commenced as of April 21st and is completed except for some minor items.
Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings has commenced as of April 28th and is completed except for a few minor items.
Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September. The work on north side is progressing on schedule. Work on the south side is anticipated to commence late June.
Queen Street Improvements June 16-20, 2025
Progress
- During the last week, the Contractor has undertaken the following activities:
Elgin to Spring
- None.
Spring to Brock
- None.
Brock to East (north side)
- Completed pouring new concrete sidewalk to East Street and matched into existing unit pavers.
- Worked on backfilling and grading boulevard areas.
- Poured concrete curbs for parking bays.
- Installed street lighting duct on Brock.
- Preparing for roadside curb.
Proposed Activities
This week the Contractor is proposing to undertake the following activities:
Elgin to Spring
- Complete outstanding deficiencies.
Spring to Brock
- Complete outstanding deficiencies.
Brock to East (north side)
- Pour new concrete roadside curbs from Brock to East.
- Install tree grates.
- Grade boulevard in preparation for unit pavers.
- Install street light poles.
Impacts
Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of May 14th, the south lane is closed between Elgin and Brock and the north lane is closed between Brock and East.
With the concrete sidewalk and most of the work finished between Elgin and Brock, except for the boulevard work between Brock and Spring on the south side, disruptions and access to businesses in these areas should be minimized.
For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Concrete sidewalk now complete on north side.
Schedule
Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings has commenced as of April 21st and is completed except for some minor items.
Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings has commenced as of April 28th and is completed except for a few minor items.
Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September. The work on north side is progressing on schedule. Work on the south side is anticipated to commence late June.
Queen Street Improvements June 9-13, 2025
Progress
During the last week, the Contractor has undertaken the following activities:
Elgin to Spring
- Completed some repairs to planter walls.
- Worked on deficiencies.
Spring to Brock
- Installed furnishings.
- Worked on deficiencies.
Brock to East (north side)
- Completed remaining tree soil cells up to East Street.
- Continued with pouring new concrete sidewalk towards East up to Civic 654.
- Installed storm drains.
- Prepared for new parking curb.
Proposed Activities
This week the Contractor is proposing to undertake the following activities:
Elgin to Spring
- Complete outstanding deficiencies.
Spring to Brock
- Complete deficiencies and repair of planter walls.
Brock to East (north side)
- Complete new concrete sidewalk up to East Street.
- Complete remaining storm drains.
- Pour new concrete parking and roadside curbs from Brock towards East.
Impacts
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of May 14th, the south lane is closed between Elgin and Brock and the north lane is closed between Brock and East.
- With the concrete sidewalk and most of the work finished between Elgin and Brock, except for the boulevard work between Brock and Spring on the south side, disruptions and access to businesses in these areas should be minimized.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Contractor will be continuing with the pouring of the new concrete sidewalk along north side and will be completed during week of June 2-6.
Schedule
Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings has commenced as of April 21st and is completed except for some minor items.
Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings has commenced as of April 28th and is completed except for a few minor items.
Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September. The work on north side is progressing on schedule.
Queen Street Improvements June 2-6, 2025
- Completed some repairs to planter walls.
- City Parks placed plantings within planters.
Spring to Brock
- Completed installation of unit pavers in south boulevard up to Brock.
- Completed some repairs to planter walls.
Brock to East (north side)
- Continued with construction of tree soil cells.
- Poured concrete sidewalk from Civic 622 to Paul Mall laneway.
- Prepared granular base for sidewalk east of Paul Mall laneway.
- Installed new catch basins.
Proposed Activities
- Complete repairs of planter walls.
- Complete installation of furnishings.
- City Parks to place plantings within planters.
- Continue with pouring new concrete sidewalk from Paul Mall laneway towards East St.
- Continue with underground pipework including storm drains.
- Complete construction of remaining tree soil cell near East St.
- Commence with construction of concrete parking curbs if timing permits.
Impacts
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of May 14th, the south lane is closed between Elgin and Brock and the north lane is closed between Brock and East.
- With the concrete sidewalk and most of the work finished between Elgin and Brock, except for the boulevard work between Brock and Spring on the south side, disruptions and access to businesses in these areas should be minimized.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Contractor will be continuing with the pouring of the new concrete sidewalk along north side.
Schedule
- Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings has commenced as of April 21st and is expected to be completed by early June.
- Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings has commenced as of April 28th and is scheduled to be completed by mid-June.
- Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September.
Queen Street Improvements May 26-30, 2025
- Installed street furnishings.
- Placed jointing sand for pavers.
- Continued with installation of unit pavers in south boulevard from plaza and to Brock.
- Completed planter wall near Brock.
- Completed removals of pavers, curbs and asphalt to East Street.
- Decommissioned and removed existing light poles.
- Constructed tree soil cell at 3 locations.
- Poured concrete sidewalk from east side of Brock to Civic 622 (50 metres).
- Installed new hydrant at Civic 672.
Proposed Activities
- Place sod in landscaped area.
- Continue with installation of street furnishings.
Spring to Brock
- Complete installation of unit pavers in south boulevard to Brock including jointing sand.
- Install street furnishings.
- Continue with pouring new concrete sidewalk from Civic 622 towards East.
- Continue with underground pipework including storm drains.
- Complete construction of tree soil cells.
Impacts
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of May 14th, the south lane is closed between Elgin and Brock and the north lane is closed between Brock and East.
- With the concrete sidewalk and most of the work finished between Elgin and Brock, except for the boulevard work between Brock and Spring on the south side, disruptions and access to businesses in these areas should be minimized.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Contractor will be continuing with the pouring of the new concrete sidewalk along north side.
Schedule
- Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings has commenced as of April 21st and is expected to be completed by early June.
- Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings has commenced as of April 28th and is scheduled to be completed by mid-June.
- Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September.
Queen Street Improvements: May 20, 2025
During the last week, the Contractor has undertaken the following activities:
Elgin to Spring
- Completed grading and placement of topsoil.
- Spring to Brock
- Continued with installation of unit pavers in south boulevard in front of plaza and towards Brock.
- Worked on planter near Brock.
Brock to East
- Continued with removals of pavers, curbs and asphalt from Brock on north side.
- Provide temporary walkway and commenced with installation of forms for pouring of new sidewalk.
- Excavated for and constructed tree soil cell.
- Completed some underground work related to sewers and water services.
This week the Contractor is proposing to undertake the following activities:
Elgin to Spring
- Place jointing sand for pavers.
- Place sod in landscaped area.
- Install furnishings (i.e. benches, waste receptacles etc.).
Spring to Brock (south side)
- Complete installation of unit pavers in south boulevard to Brock including jointing sand.
- Complete work on planter.
- Brock to East (north side)
- Finish removals of pavers, curbs and asphalt on north side.
- Continue with underground pipework (i.e. curb stops, drains etc.) including installation of new hydrant near East Street (May 23).
- Continue with construction of tree soil cells.
- Commence with pouring new concrete sidewalk from Brock.
- Remove existing streetlights.
Impacts
Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings has commenced as of April 28th and is scheduled to be completed by mid-June.
Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September.
Queen Street Improvements: May 12-16, 2025
- Installed street furnishings.
- Placed jointing sand for pavers.
- Continued with installation of unit pavers in south boulevard from plaza and to Brock.
- Completed planter wall near Brock.
- Completed removals of pavers, curbs and asphalt to East Street.
- Decommissioned and removed existing light poles.
- Constructed tree soil cell at 3 locations.
- Poured concrete sidewalk from east side of Brock to Civic 622 (50 metres).
- Installed new hydrant at Civic 672.
Proposed Activities
- Place sod in landscaped area.
- Continue with installation of street furnishings.
Spring to Brock
- Complete installation of unit pavers in south boulevard to Brock including jointing sand.
- Install street furnishings.
- Continue with pouring new concrete sidewalk from Civic 622 towards East.
- Continue with underground pipework including storm drains.
- Complete construction of tree soil cells.
Impacts
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. As of May 14th, the south lane is closed between Elgin and Brock and the north lane is closed between Brock and East.
- With the concrete sidewalk and most of the work finished between Elgin and Brock, except for the boulevard work between Brock and Spring on the south side, disruptions and access to businesses in these areas should be minimized.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible. Contractor will be continuing with the pouring of the new concrete sidewalk along north side.
Schedule
- Elgin to Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings has commenced as of April 21st and is expected to be completed by early June.
- Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings has commenced as of April 28th and is scheduled to be completed by mid-June.
- Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings has commenced as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September.
Queen Street Improvements: May 15-16, 2025
East Street to Brock Street
Queen Street Improvements: May 15, 2025
SSM Museum – 10a.m. to 4p.m.
Case’s Music – 11a.m. to 9p.m.
Sewing Chambers – 10a.m. to 5p.m.
Mane Street Salon and Spa – 10a.m. to 10p.m.
The Aesthetic Studio – 10a.m. to 7p.m.
Loyalty Forge – 9a.m. to 5p.m.
Queen Street Improvements: May 5, 2025
Elgin to Spring
- Worked on completing installation of unit pavers in boulevard on south side.
- Set up traffic control for closure of south lane.
- Removed temporary asphalt within the south boulevard.
- Commenced with installation of unit pavers in south boulevard from Spring towards Brock.
- Commenced work on planters.
- Complete remaining unit pavers and place jointing sand.
- Undertake landscaping tasks including fine grading and landscaping behind sidewalk.
- Continue with installation of unit pavers in south boulevard.
- Continue work on planters.
- Set up traffic control for closure of north lane.
- Commence with removals on north side.
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. Starting May 7th, the north lane will be closed between Brock and East.
- With the concrete sidewalk and most of the work finished between Elgin and Brock, except for the boulevard work between Brock and Spring on the south side, disruptions and access to businesses in these areas should be minimized.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible.
Spring to Brock – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings has commenced as of April 28th and is scheduled to be completed by mid-June.
Brock to East – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings will commence as of May 7th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September.
Queen Street Improvements: April 28, 2025
- Mobilized equipment, manpower and materials to the site.
- Set up traffic control for lane closure (Elgin and March).
- Commenced with completing outstanding work including remaining pavers (Elgin and March).
- Proposed Activities
- Mobilizing additional equipment, manpower and materials to the site.
- Complete installation of unit pavers in boulevard (Elgin to March).
- Undertake landscaping tasks (Elgin to March).
- Set up traffic control for closure of south lane (Spring to Brock).
- Remove temporary asphalt from south boulevard area (Spring to Brock).
- Prepare for and commence with installation of unit pavers in south boulevard (Spring to Brock).
Impacts
- Queen Street will be reduced to one lane at various locations and times until all work is completed between Elgin and East. Starting the week of April 28th, the south lane closure will include the block between Elgin and Brock.
- With the concrete sidewalk and most of the work finished between Elgin and Brock, except for the boulevard work between Brock and Spring on the south side, disruptions and access to businesses in these areas should be minimized.
- For the new work between Brock and East, it will be staged similarly to last year’s work, with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible.
- Elgin and Spring – The remaining boulevard work, including unit pavers, landscaping and furnishings has commenced as of April 21st and is expected to be completed by early June.
- Brock and Spring – The remaining boulevard work involving unit pavers, planters, landscaping and furnishings has commenced as of April 28th and is scheduled to be completed by mid-June.
- East and Brock – Work in this block, including removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers and furnishings will commence May 6th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September.
Queen Street Improvements: April 21, 2025
- Mobilizing equipment, manpower and materials to the site.
- Obtaining utility locates.
- Coordinating pre-construction building survey (Brock to East)
- Setting up traffic control for lane closures (Elgin to Spring).
- Commence with completing outstanding work, including remaining pavers and related work. (Elgin to Spring).
- Queen Street will be reduced to one lane of traffic at various locations and times until all work is completed between Elgin and East. During the week of April 21st, the lane closure will be limited to the stretch between Elgin and Spring.
- With the concrete sidewalk and most of the work finished between Elgin and Brock, except for the boulevard work between Brock and Spring on the south side, disruptions and access to businesses in these areas should be minimized.
- For the new work between Brock and East, it will be staged similarly to last year’s work with the north side generally being completed first before moving to the south side. Once the hard surfaces (like concrete and unit pavers) are removed, temporary walkways will be set up to allow access to businesses. If a walkway needs to be closed, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever possible.
- The remaining boulevard work between Elgin and Spring, which includes pavers, landscaping, and furnishings, will begin on April 21st and is expected to be completed by early June.
- The remaining boulevard work between Brock and Spring, including pavers, planters, landscaping, and furnishings, is scheduled to start on April 28th and be completed by mid-June.
- The work between East and Brock, encompassing removals, upgrades to underground services, soil cells, concrete curbs and sidewalks, unit pavers, and furnishings, will commence May 6th. Most of the work, including final paving, is anticipated to be completed by mid-August, with the final boulevard work finishing up by mid-September.
2024 Progress
September – December
Queen Street Improvements: December 4, 2024
- The temporary all-way stop will be removed
- A new Pedestrian Crossover (PXO) will be installed
- The intersection will transition to a two-way stop, with Spring Street controlled by a stop sign and Queen Street maintaining the right-of-way
Brock Street and Queen Street
- The temporary all-way stop will be removed
- Traffic signals at this intersection will be activated to regulate traffic flow
Queen Street Improvements: November 26, 2024
During the last week, the Contractor has completed the following activities:
Elgin to March
March to Spring
Spring to Brock
🚧Proposed Activities🚧
This week the Contractor is proposing to undertake the following activities:
Elgin to March
Brock Intersection
Elgin to East of Brock
🚧Impacts🚧
• Queen Street will continue to be reduced to a single lane of traffic throughout this week, with reopening scheduled for November 29th.
🚧Schedule🚧
• The final lift of asphalt has been completed within the current contract limits.
Queen Street Improvements: November 12, 2024
- Placed final lift of asphalt surface course.
- Completed unit pavers.
- Completed landscaping.
- Completed concrete sidewalk to Elgin.
- Graded boulevard and pour concrete bases for tree grates and planter walls.
- Installed and energized new street lighting.
- Placed final lift of asphalt surface course.
- Continued with installing unit pavers.
- Poured concrete sidewalk at southwest corner Brock.
- Complete concrete curb to Brock and curb for parking bay.
- Completed electrical to Brock and installed new street lighting.
- Graded boulevard with preparing boulevard for unit pavers.
- Place pavement markings.
- Place final lift of asphalt on parking bay.
- Plant trees.
- Complete concrete curb for parking bay and pave parking bay.
- Complete grading work in boulevard.
- Commence with installation of planter walls and unit pavers.
- Continue with installation of unit pavers.
- Place asphalt binder courses (Wednesday)
- Complete electrical and traffic ducts in Brock intersection.
- Connect and energize new street lighting.
- Pour concrete curbs and sidewalk at Brock intersection.
- Grade and place temporary asphalt in boulevard (Note: unit pavers and planters will be installed next spring).
- Queen Street will be closed between Brock and Spring on Wednesday, November 13th, to complete placement of the asphalt binder courses. Both the Brock and Spring intersections will remain open.
- Queen Street will continue to be reduced to a single lane of traffic throughout the construction.
- The Contractor will continue with the remaining boulevard work on the south side of Queen. Access to the businesses will be maintained via the new sidewalk. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- There may be occasional short-term closures of Queen Street and its side streets. Advance notification will be provided for any closures.
- There are no further planned water outages.
- The final lift of asphalt has been completed from east side of Spring to Elgin. The remaining asphalt binder courses between Brock and Spring will be done this week, with the final lift of asphalt scheduled for next week.
- Work within the Brock intersection, including new traffic signals, is scheduled to be completed by late November.
- On the north side of Queen, all boulevard area work is completed except for plantings and street furnishings, which are scheduled for next spring.
- On the south side of Queen, the remaining work includes unit pavers and planters. This work is ongoing and is scheduled to be completed between Spring and Elgin by late November. The installation of the unit pavers and planters between Spring and Brock has been delayed until next spring and in the interim the boulevard will be paved.
- Outstanding work to be done next year, will commence early in the spring once conditions allow.
Elgin to Spring Street
Silver Threads – 10 a.m. to 4 p.m.
Queen Street Improvements: November 4, 2024
- Placed second lift of asphalt binder course.
- Continued placing unit pavers.
- Completed planter retaining walls.
- Completed electrical ducts for new street lighting and receptacles.
- Poured concrete sidewalk to within 50m of Elgin.
- Poured portion of concrete barrier curb for parking bay.
- Placed second lift of asphalt binder course.
- Commenced with installing unit pavers.
- Completed placement of first lift of asphalt binder course.
- Completed concrete sidewalk to Brock.
- Poured the concrete barrier curb for the parking bay.
- Installed electrical ducts for new street lighting and receptacles up to Brock.
- Commenced with preparing boulevard for unit pavers.
- Adjust manholes and water valve boxes to finish grade.
- Place asphalt surface course (Thursday and Friday).
- Complete the installation of unit pavers in boulevard and grass restoration work.
South side
- Complete concrete sidewalk at Elgin and curb for parking bay.
- Grade boulevard and pour concrete bases for tree grates and planter walls.
- Commence with installation of unit pavers.
- Install and energize new street lighting.
March to Spring
South side
- Continue with install unit pavers.
- Pour concrete sidewalk at southwest corner Brock.
- Complete concrete curb to Brock and curb for parking bay.
- Commence with installation of unit pavers.
- Place asphalt binder courses.
- Wednesday, November 6th: Queen Street (West side of March to East side of Elgin), excluding the March and Elgin intersections which will remain open.
- Thursday, November 7th & Friday, November 8th: Queen Street (West side of Brock to East side of Elgin), including the closure of the Spring and March intersections but excluding Brock and Elgin which will remain open.
- As of October 5, 2024, Queen Street has been opened to one lane of traffic throughout the limits to Elgin Street.
- Queen Street will continue to be reduced to a single lane of traffic throughout the construction.
- The Contractor will be continuing with the remaining removals of the hard surfaces and pouring the new sidewalk on the south side between Spring & Brock and March & Elgin. Temporary walkways will be provided along the buildings to access the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- There may be occasional short-term closures of Queen Street and its side streets. Advance notification will be provided for any closures.
- There are no further planned water outages.
- The underground work and roadway restoration between March and Elgin was completed and Queen reopened as of October 5th. Work within the parking bays and boulevard areas will continue on both sides of Queen.
- The work is scheduled to be substantially completed by mid-November, pending weather conditions, with boulevard work continuing into later November and some work extending into 2025 depending upon on the final project limits.
Queen Street Improvements: October 28, 2024
Elgin to March
- Continued with placement of unit pavers.
- Constructing planter retaining walls (3).
- Completed some grading and grass restoration.
- Removed unit pavers.
- Removed existing street lighting.
- Installed electrical duct for new street lighting.
- Graded boulevard in preparation for unit pavers.
- Poured pedestrian ramps at Spring intersection.
- Installed new traffic signal poles.
- Continued with removals.
- Poured concrete sidewalk from Spring to just west of Brock.
- Poured pedestrian ramp and roadway curb at Spring.
- Complete installation of unit pavers in boulevard.
- Complete planter retaining walls.
- Complete installation of ducts for new street lighting and receptacles.
- Pour concrete sidewalk and curb for parking bay.
- Grade boulevard and pour concrete bases for tree grates and planter walls.
- Pour concrete ramp at Spring.
- Commence with installation of unit pavers.
- Place asphalt binder course.
- Complete underground work and install electrical ducts.
- Pour remaining concrete sidewalk to Brock.
- Continue with pouring of concrete curb to Brock and curb for parking bay.
- Place asphalt binder course.
- As of October 5, 2024, Queen Street has been opened to one lane of traffic throughout the limits to Elgin Street.
- Queen Street will continue to be reduced to a single lane of traffic throughout the construction.
- The Contractor will be continuing with the remaining removals of the hard surfaces and pouring the new sidewalk on the south side between Spring & Brock and March & Elgin. Temporary walkways will be provided along the buildings to access the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- There may be occasional short-term closures of Queen Street and its side streets. Advance notification will be provided for any closures.
- There are no further planned water outages.
- The work on Queen Street between March Street and Brock Street commenced from March Street and is mostly complete. Traffic now diverted to north side as of September 9th and construction activities continues on south side.
- The underground work and roadway restoration between March and Elgin was completed and Queen reopened as of October 5th. Work within the parking bays and boulevard areas will continue on both sides of Queen.
- The work is scheduled to be Substantially completed early November, pending weather conditions, with boulevard work continuing in November and some work extending into 2025 depending upon on the final project limits.
Queen Street Improvements: October 21, 2024
Queen Street Improvements: October 15, 2024
- Poured roadway curbs at Elgin intersection.
- Poured concrete sidewalk at March intersection and 20 metres west on north side.
- Completed grading of boulevard area along the north side to Elgin.
- Prepared for new concrete parking curb and sidewalk.
- Poured concrete ramp at March.
- Worked on remaining unit pavers at March.
- Energized new power supply for street lighting.
- Completed grading of boulevard area.
- Poured concrete sidewalk.
- Completed installation of unit pavers east of Brock.
- Energized new power supply for street lighting.
- Continued with removals.
- Completed construction of soil cells.
- Installed new catch basin.
- Pour concrete sidewalk on north side to Elgin.
- Pour concrete curb for parking bay on north side.
- Prepare and commence with installation of unit pavers in boulevard on north side.
- Install new street light poles on north side.
- Complete remaining unit pavers at March.
- Pour concrete bases for tree grates.
- Prepare and commence with installation of unit pavers.
- Install new street light poles.
- Complete installation of unit pavers east side of Brock.
- Carry out grading of boulevard and roadway.
- Install electrical ducts.
- Prepare for and pour roadway curb from Spring.
- As of October 5, 2024, Queen Street has been opened to one lane of traffic throughout the limits to Elgin Street.
- With traffic now diverted to the north side between March and west side of Brock, the Contractor will be continuing removals of the hard surfaces (such as concrete & unit pavers) along the businesses on the south side between Spring and Brock. Temporary walkways will be provided along the buildings to access the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- During the construction process, Queen Street will be reduced to a single lane of traffic while the Contractor works on half of Queen Street at a time.
- There may be occasional short-term closures of Queen Street and its side streets. Advance notification will be provided for any closures.
- There are no further planned water outages.
- The work on Queen Street between March Street and Brock Street commenced from March Street and is mostly complete. Traffic now diverted to north side as of September 9th and construction activities continues on south side.
- The underground work and roadway restoration between March and Elgin was completed and Queen reopened as of October 5th. Work within the parking bays and boulevard areas will continue on both sides of Queen.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
Email us at queenstreet@averyconstruction.ca
Queen Street Improvements: October 7, 2024
- Completed final commissioning of new watermain with final connection at Elgin Street.
- Completed storm sewer upgrades.
- Completed soil cells.
- Poured roadway curbs throughout limit except at Elgin.
- Completed roadway granulars and placement of asphalt binder course within roadway.
- Completed installation of tree grates.
- Placed jointing sand within unit paver boulevard.
- Removed temporary construction fencing.
- Installed electrical ducts for new street lighting.
- Completed grading of boulevard area.
- Placed asphalt binder course within roadway.
- Continued with installation of unit pavers east of Brock.
- Completed installation of tree grates.
- Placed jointing sand with unit paver boulevard up to Brock.
- Removed temporary construction fencing up to Brock.
- Continued with removals.
- Commenced with construction of soil cells, east of Spring.
- Complete curb and asphalt at Elgin.
- Carry out grading of boulevard areas.
- Prepare and pour concrete sidewalk on north side.
- Commence with concrete curbs for parking bays.
- Complete concrete curb and ramp at NE corner.
- Complete grading of boulevard.
- Commence with preparation and pouring of concrete sidewalk.
- Complete installation of unit pavers east side of Brock.
- Complete soil cells on east side of Spring.
- Complete storm sewer upgrades.
- Install electrical ducts.
- As of October 5, 2024, Queen Street has been opened to one lane of traffic throughout the limits to Elgin Street.
- With traffic now diverted to the north side between March and west side of Brock, the Contractor will be continuing removals of the hard surfaces (such as concrete & unit pavers) along the businesses on the south side between Spring and Brock. Temporary walkways will be provided along the buildings to access the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- During the construction process, Queen Street will be reduced to a single lane of traffic while the Contractor works on half of Queen Street at a time.
- There may be occasional short-term closures of Queen Street and its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. There are no further planned water outages.
- The work on Queen Street between March Street and Brock Street commenced from March Street and is mostly complete. Traffic now diverted to north side as of September 9th and construction activities continues on south side.
- The underground work and roadway restoration between March and Elgin was completed and Queen reopened as of October 5th. Work within the parking bays and boulevard areas will continue on both sides of Queen.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
Queen Street Improvements: October 1, 2024
- Commissioned new watermain with connections at March Street, Post Office and 4 services.
- Worked on storm sewer upgrades.
- Constructed soil cells on south side.
- Worked on backfilling and construction of road subbase.
- Poured roadway curb along south side from March to west side of Post Office.
- Worked on installing tree grates.
- Installed power supply cabinets on March for new street lighting.
- Completed soil cells.
- Completed storm sewer upgrades.
- Poured roadside curb.
- Completed planters with placement of planting soil.
- Continued with installation of unit pavers within boulevard areas to east side of Brock.
- Installed power supply cabinets on Brock for new street lighting.
- Complete final watermain connection at Elgin (Oct 1).
- Complete soil cells on north side.
- Complete remaining storm sewer upgrades at Elgin.
- Reconstruct roadway with placement of granulars.
- Pour remaining roadway concrete curbs on both sides.
- Place asphalt binder course full width of roadway.
- Place jointing sand for unit pavers and complete tree grates.
- Complete wiring of new power supply cabinets for new street lighting on March.
- Undertake grading of boulevard area.
- Pave asphalt binder course.
- Complete installation of unit pavers to east side of Brock.
- Complete wiring of new power supply cabinets for new street lighting on Brock.
- Queen Street will be closed between Spring and March commencing Thursday, October 3rd for 2 days to allow completion of the asphalt paving from Spring through to Elgin. Advance notification has been provided.
- With traffic now diverted to the north side between March and west side of Brock, the Contractor will be continuing removals of the hard surfaces (such as concrete & unit pavers) along the businesses on the south side between Spring and Brock. Temporary walkways will be provided along the buildings to access the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- Queen Street between March and Elgin is CLOSED as of Monday, August 26th for a period of six (6) weeks to complete the replacement of the u/g sanitary sewer, watermains and appurtenances.
- During the construction process, Queen Street will be reduced to a single lane of traffic while the Contractor works on half of Queen Street at a time.
- There may be occasional short-term closures of Queen Street and its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. To complete the remaining connection of the new watermain at Elgin, there is an outage planned for Tuesday, October 1st. Impacted businesses on Queen between March and Elgin have been notified.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side. As of September 9th, the work has commenced on the south side from March Street and will continue towards Brock Street.
- The work between March and Elgin commenced week of August 6th with the closure of Queen effective as of August 26, 2024 for 6-weeks and is scheduled to reopen on or before October 7th.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
Queen Street Improvements: September 24, 2024
- Completed installation of new watermain including testing, swabbing and disinfection.
- Completed installation of new sanitary sewer.
- Worked on backfilling and construction of road subbase.
- Cleaned up unit pavers within boulevard area in preparation for jointing sand.
- Completed installation of ducts across Queen.
- Excavated and constructed soil cells (4).
- Worked on storm sewer upgrades.
- Completed installation of precast concrete block retaining walls for planters.
- Continued with installation of unit pavers within boulevard areas.
- Worked on removals of concrete & pavers within boulevard (approx. 30 metres east of Spring).
- Constructed temporary walkway and erected fencing.
- Undertake commissioning of new watermain including connections to existing distribution system.
- Complete reconstruction of roadway and prepare for new concrete curbs.
- Commence with pouring of new concrete curb along south side.
- Commence with excavation of soil cells on north side
- Complete storm sewer upgrades.
- Place jointing sand for unit pavers and install tree grates.
- Install and complete wiring of new power supply cabinets for new street lighting on March.
- Complete remaining soil cell and backfill all soil cells.
- Commence with pour of concrete curb.
- Complete installation of unit pavers to east side of Brock.
- Install and complete wiring of new power supply cabinets for new street lighting on Brock.
- Queen Street will be closed between Spring and March commencing Monday, September 23rd for 4 days to allow completion of the final watermain connection and other work within the March intersection. Advance notification has been provided.
- With traffic now diverted to the north side between March and west side of Brock, the Contractor will be continuing removals of the hard surfaces (such as concrete & unit pavers) along the businesses on the south side between Spring and Brock. Temporary walkways will be provided along the buildings to access the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- Queen Street between March and Elgin is CLOSED as of Monday, August 26th for a period of six (6) weeks to complete the replacement of the u/g sanitary sewer, watermains and appurtenances.
- During the construction process, Queen Street will be reduced to a single lane of traffic while the Contractor works on half of Queen Street at a time.
- There may be occasional short-term closures of Queen Street and its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. To complete the final commissioning and connections for the new watermain between Elgin and March, there are outages planned for the week of September 23rd. Impacted businesses on Queen and March have been notified.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side. As of September 9th, the work has commenced on the south side from March Street and will continue towards Brock Street.
- The work between March and Elgin commenced week of August 6th with the closure of Queen effective as of August 26, 2024 for 6-weeks until October 7th.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
- While we understand that the construction will cause some inconvenience to the adjacent business and property owners, every effort will be made to minimize the disruptions, where possible.
Queen Street Improvements Update: September 23, 2024
- Completed installation of new watermain including testing, swabbing and disinfection.
- Completed installation of new sanitary sewer.
- Worked on backfilling and construction of road subbase.
- Cleaned up unit pavers within boulevard area in preparation for jointing sand.
- Completed installation of ducts across Queen.
- Excavated and constructed soil cells (4).
- Worked on storm sewer upgrades.
- Completed installation of precast concrete block retaining walls for planters.
- Continued with installation of unit pavers within boulevard areas.
- Worked on removals of concrete & pavers within boulevard (approx. 30 metres east of Spring).
- Constructed temporary walkway and erected fencing.
- Undertake commissioning of new watermain including connections to existing distribution system.
- Complete reconstruction of roadway and prepare for new concrete curbs.
- Commence with pouring of new concrete curb along south side.
- Commence with excavation of soil cells on north side
- Complete storm sewer upgrades.
- Place jointing sand for unit pavers and install tree grates.
- Install and complete wiring of new power supply cabinets for new street lighting on March.
- Complete remaining soil cell and backfill all soil cells.
- Commence with pour of concrete curb.
- Complete installation of unit pavers to east side of Brock.
- Install and complete wiring of new power supply cabinets for new street lighting on Brock.
- Queen Street will be closed between Spring and March commencing Monday, September 23rd for 4 days to allow completion of the final watermain connection and other work within the March intersection. Advance notification has been provided.
- With traffic now diverted to the north side between March and west side of Brock, the Contractor will be continuing removals of the hard surfaces (such as concrete & unit pavers) along the businesses on the south side between Spring and Brock. Temporary walkways will be provided along the buildings to access the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- Queen Street between March and Elgin is CLOSED as of Monday, August 26th for a period of six (6) weeks to complete the replacement of the u/g sanitary sewer, watermains and appurtenances.
- During the construction process, Queen Street will be reduced to a single lane of traffic while the Contractor works on half of Queen Street at a time.
- There may be occasional short-term closures of Queen Street and its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. To complete the final commissioning and connections for the new watermain between Elgin and March, there are outages planned for the week of September 23rd. Impacted businesses on Queen and March have been notified.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side. As of September 9th, the work has commenced on the south side from March Street and will continue towards Brock Street.
- The work between March and Elgin commenced week of August 6th with the closure of Queen effective as of August 26, 2024 for 6-weeks until October 7th.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
- While we understand that the construction will cause some inconvenience to the adjacent business and property owners, every effort will be made to minimize the disruptions, where possible.
Queen Street Improvements: September 9, 2024
- Continued with installation of new watermain towards Elgin.
- Commenced with installation of new sanitary sewer from Civic 444 toward Elgin.
- Constructed soil cell near Civic 458.
- Continued with installation of unit pavers in boulevard.
- Completed wiring for new street light poles.
- Diverted traffic to south side of Queen
- Poured concrete curbs and pedestrian ramps at NW and NE corner of Brock.
- Completed paving within the north side of the Brock intersection.
- Commenced with installation of precast concrete block retaining walls for planters.
- Completed wiring for new street light poles.
- Diverted traffic to south side of Queen up to west side of Brock.
- Continue with installation of new watermain and sanitary sewer towards Elgin.
- Complete backfilling and restoration of roadway behind pipe operations.
- Complete installation of remaining unit pavers in boulevard.
- Energize new street lighting from a temporary supply.
- Commence with removals of hard surfaces (pavers, curb, asphalt etc.) from March towards Spring.
- Construct temporary walkway and install fencing.
- Commence with soil cells.
- Complete concrete sidewalk on NW and NE corners of Brock.
- Commence with installation of unit pavers and continue with precast retaining wall for planters.
- Energize new street lighting from a temporary supply.
- With traffic now diverted to the north side between March and west side of Brock, the Contractor will be undertaking removals of the hard surfaces (such as concrete & unit pavers) along the businesses on the south side commencing from March Street and working towards Brock. Temporary walkway will be provided along the buildings to access the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- Queen Street between March and Elgin is CLOSED as of Monday, August 26th for a period of six (6) weeks to complete the replacement of the u/g sanitary sewer, watermains and appurtenances.
- During the construction process, Queen Street will be reduced to a single lane of traffic while the Contractor works on half of Queen Street at a time.
- There may be occasional short-term closures of Queen Street and its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side. As of September 9th, the work has commenced on the south side from March Street and will continue towards Brock Street.
- The work between March and Elgin has commenced week of August 6th with the closure of Queen commencing as of August 26, 2024 for 6-weeks until early October.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
Queen Street Improvements: September 3, 2024
During the last week, the Contractor has completed the following activities:
- Closed Queen Street between March and Elgin as of Monday, August 26th for 6 weeks.
- Connected temporary water system for Civic No.’s 446, 454, 458 & 464.
- Commenced with installation of new watermain, services and hydrant from March.
- Completed sanitary sewer repair at Civic 458.
📍March to Spring (north side)
- Continued with installation of unit pavers in boulevard.
- Prepared and completed paving of 1st lift of asphalt along north side of Queen.
- Installed new street light poles.
- Installed bases for new power supply cabinets on March.
📍Spring to Brock (north side)
- Poured concrete sidewalk & ramp at Spring and curb at Brock and various locations.
- Prepared and completed paving of 1st lift of asphalt for parking bay and north side of Queen from west side of Brock.
- Poured concrete bases for planter retaining walls.
- Installed new street light poles.
🚧Proposed Activities🚧
📍Elgin to March
- Continue with installation of new watermain towards Elgin.
- Commence with installation of new sanitary sewer starting at Civic 446 towards Elgin.
📍March to Spring (north side)
- Complete installation of unit pavers in boulevard.
- Complete wiring of new street light poles.
- Complete power supply on March Street for new street lighting.
📍Spring to East of Brock (north side)
- Complete concrete curbs and ramps at Brock intersection and misc. sidewalk patches.
- Commence with installation of unit pavers and precast retaining wall for planters.
- Complete paving of 1st lift of asphalt on Queen through Brock intersection later in week during 2-day closure of Brock.
- Complete wiring of new street light poles.
- Complete power supply on Brock Street for new street lighting.
🚧Impacts🚧
- Brock Street, north of Queen Street, is scheduled to be closed as of Thursday, September 5th and Friday, September 6th to complete paving work. Access will be maintained to businesses on Brock from Albert.
- Queen Street vehicular traffic is scheduled to be diverted to the north side of Queen as of the end of week to allow work to commence on the south side. The diversion may be done in stages.
- Queen Street between March and Elgin is CLOSED as of Monday, August 26th for a period of six (6) weeks to complete the replacement of the u/g sanitary sewer, watermains and appurtenances.
- The Contractor has completed much of the work on the new concrete sidewalk between March to Brock except at new pole locations and at intersections where temporary platforms/ramps have been provided. Pedestrians have been diverted to new concrete sidewalk.
- During the construction process, Queen Street will be reduced to a single lane of traffic and one parking lane while the Contractor works on half of Queen Street at a time. One lane is now closed between March and Brock Street on north side.
- Once the hard surfaces (such as concrete & unit pavers) are removed, temporary walkways will be established to allow access to the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- There may be occasional short-term closures of Queen Street and its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages.
🚧Schedule🚧
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side. The traffic is scheduled to be diverted to the north side late in the week of September 3rd at which time work will commence on the south side of Queen the week of September 9th.
- The work between March and Elgin has commenced week of August 6th with the closure of Queen commencing as of August 26, 2024 for 6-weeks until early October.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
- While we understand that the construction will cause some inconvenience to the adjacent business and property owners, every effort will be made to minimize the disruptions, where possible.
July – August
Queen Street Improvements: August 27, 2024
- Installed and commissioned temporary water system for Civic No.’s 446, 454, 458 & 464.
- Set up traffic control for closure of Queen Street at March commencing Monday, March 26th for 6 weeks.
- Commenced with installation of unit pavers in boulevard.
Spring to Brock (north side)
- Poured concrete curb along roadway.
- Commenced with installation of new street light poles and associated wiring.
- Completed underground electrical and traffic work at the Brock intersection
- Close Queen Street between March and Elgin (August 26th).
- Complete connections to temporary water system for Civic No.’s 446, 454, 458 & 464 (August 26th).
- Complete capping of existing watermain at mid-block (August 27th).
- Carry out removals of asphalt, concrete curbs etc. from March towards Elgin along south side and install temporary walkways.
- Commence with installation of new sanitary sewer and watermain from March towards Elgin.
- Continue with installation of unit pavers in boulevard.
- Prepare and complete paving of travel lane within roadway.
- Install new street light poles and associated wiring.
- Complete power supply on March Street for new street lighting following completion of work by PUC.
- Complete concrete curbs and ramps at intersections.
- Work on new planters.
- Prepare and complete asphalt paving within parking areas and roadway.
- Install new street light poles and associated wiring.
- Complete power supply on Brock Street for new street lighting following completion of work by PUC.
- Queen Street between March and Elgin will be CLOSED commencing today Monday, August 26th for a period of six (6) weeks to complete the replacement of the u/g sanitary sewer, watermains and appurtenances.
- A water outage is planned for the businesses west of March along north side and post office on Tuesday, August 27th. All impacted businesses/agencies have been notified in advance.
- The Contractor has completed much of the work on the new concrete sidewalk between March to Brock except at new pole locations and at intersections where temporary platforms/ramps have been provided. Pedestrians have been diverted to new concrete sidewalk.
- During the construction process, Queen Street will be reduced to a single lane of traffic and one parking lane while the Contractor works on half of Queen Street at a time. One lane is now closed between March and Brock Street on north side.
- Once the hard surfaces (such as concrete & unit pavers) are removed, temporary walkways will be established to allow access to the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- There may be occasional short-term closures of Queen Street and its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side. It is expected that traffic will be diverted to the north side week of September 3rd at which time work will commence on the south side of Queen.
- The work between March and Elgin has commenced week of August 6th with the closure of Queen commencing as of August 26, 2024 for 6-weeks until early October.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
Queen Street Improvements: August 19, 2024
- Completed cut and capping of existing watermain within the March Street intersection in preparation for new watermain.
- Installed new electrical ducts across March Street.
- Completed fine grading and other work on tree grates in preparation for the unit pavers.
- Placed asphalt in parking bay.
- Completed concrete ramp at Spring intersection.
- Poured concrete parking curbs.
- Continued with underground electrical and traffic work at the Brock intersection.
- Install temporary water system for Civic No.’s 446, 454, 458 & 464.,.
- Install electrical ducts on March to power supply.
- Set up traffic control for closure of Queen Street at March commencing Monday, March 26th for 6 weeks.
- Commence with installation of unit pavers in boulevard.
- Prepare for paving of travel lane and complete paving if timing permits.
- Commence with installation of new street light pole and new supply from March Street later in week or following week.
- Complete pouring of concrete curbs and ramps.
- Asphalt paving.
- Complete electrical work within the Brock intersection including ducts, traffic pole foundations etc.
- Queen Street between March and Elgin will be CLOSED commencing Monday, August 26th for a period of six (6) weeks to complete the replacement of the u/g sanitary sewer, watermains and appurtenances.
- The Contractor has completed much of the work on the new concrete sidewalk between Spring to Brock except at new pole locations and at intersections where temporary platforms/ramps have been provided. Pedestrians have been diverted to new concrete sidewalk.
- During the construction process, Queen Street will be reduced to a single lane of traffic and one parking lane while the Contractor works on half of Queen Street at a time. One lane is now closed between March and Brock Street on north side.
- Once the hard surfaces (such as concrete & unit pavers) are removed, temporary walkways will be established to allow access to the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- There may be occasional short-term closures of Queen Street and its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side.
- The work between March and Elgin is scheduled to commence week of August 6th with closure of Queen scheduled to commence as of August 26, 2024 for 6-weeks.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
Queen Street Improvements: August 12, 2024
- Completed removals of asphalt, concrete curbs and unit pavers and installed temporary walkway between March and courthouse east entrance.
- Poured new concrete barrier curb at Spring intersection.
- Worked on grading of boulevard and parking areas.
- Completed pouring new concrete sidewalk to Brock (except at pole locations).
- Worked on grading of boulevard and parking areas.
- Completed underground electrical and traffic work on northeast corner of the Brock intersection.
- Set up traffic control for closure of March Street at Queen commencing Tuesday, March 13th for 3 days.
- Complete cut and capping of existing watermain within the March Street intersection in preparation for new watermain.
- Complete work on soil cells including concrete curbs for tree grates.
- Pour concrete ramps at Spring intersection.
- Prepare for unit pavers.
- Receive new street light poles and commence with installation if timing permits.
- Pour concrete curbs for parking bays and along roadway.
- Continue with electrical work within the Brock intersection including ducts, traffic pole foundations etc.
- March Street between Queen and Albert will be CLOSED commencing Tuesday, August 13th for a period of three (3) days to complete work relating on the existing watermain at the Queen intersection. Access to the businesses on Brock between Queen and Albert will be maintained.
- To complete cut & capping of existing watermain at March there will be a local water outage on August 14th but it will NOT impact any businesses except Civic 472 Queen.
- The Contractor will be continuing with work on the new concrete sidewalk between Spring to Brock this week which will require rerouting of the temporary walkway to complete concrete pours. Access will be maintained to the local businesses from temporary walkway via temporary platforms and other pedestrians walking through will be directed to the south side of Queen. Once completed, pedestrians will be diverted to new concrete sidewalk.
- During the construction process, Queen Street will be reduced to a single lane of traffic and one parking lane while the Contractor works on half of Queen Street at a time. One lane is now closed between March and Brock Street on north side.
- Once the hard surfaces (such as concrete & unit pavers) are removed, temporary walkways will be established to allow access to the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- Queen Street from Elgin to March will be fully closed for a period of six weeks commencing as of August 26, 2024. Additionally, there may be occasional short-term closures of Queen Street its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side.
- The work between March and Elgin is scheduled to commence week of August 6th with closure of Queen scheduled to commence as of August 26, 2024 for 6-weeks.
- The work is scheduled to be substantially completed late this fall, with some work extending into 2025 depending on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
- While we understand that the construction may cause some inconvenience to the adjacent business and property owners, every effort will be made to minimize the disruptions, where possible.
- Brock to Spring Street
Queen Street Improvements: August 9, 2024
- Poured new concrete barrier curb at back of the parking bay.
- Poured new concrete curb and gutter along roadway.
- Replaced hydrant just east of the Brock.
- Constructed tree soil cell just east of Brock.
- Continued with installing formwork for new sidewalk.
- Poured new concrete sidewalk from Spring to mid-way to Brock.
- Completed underground electrical and traffic work on north side of the Brock intersection.
- Commence with removal of unit pavers and installation of temporary walkway between March and courthouse east entrance.
- Pour concrete curbs at Spring intersection.
- Undertake preparation of boulevard area for placement of unit pavers.
- Prepare for March Street closure scheduled for next week.
- Complete pouring of new concrete sidewalk to Brock (except at pole locations).
- Commence with concrete curb.
- Continue with electrical work within the Brock intersection including ducts, traffic pole foundations etc.
- The Contractor will be continuing with work on the new concrete sidewalk between Spring to Brock this week which will require rerouting of the temporary walkway to complete concrete pours. Access will be maintained to the local businesses from temporary walkway via temporary platforms and other pedestrians walking through will be directed to the south side of Queen. Once completed, pedestrians will be diverted to new concrete sidewalk.
- During the construction process, Queen Street will be reduced to a single lane of traffic and one parking lane while the Contractor works on half of Queen Street at a time. One lane is now closed between March and Brock Street on north side.
- Once the hard surfaces (such as concrete & unit pavers) are removed, temporary walkways will be established to allow access to the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- Queen Street from Elgin to March will be fully closed for a period of six weeks commencing as of August 26, 2024. Additionally, there may be occasional short-term closures of Queen Street its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side.
- The work between March and Elgin is scheduled to commence week of August 6th with closure of Queen scheduled to commence as of August 26, 2024 for 6-weeks.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
Queen Street Improvements: July 31, 2024
Queen Street Improvements: July 30, 2024
Reminder:
Queen Street Improvements: July 29, 2024
- Poured new concrete sidewalk, except at new pole locations.
- Preparing for new concrete curb at back of the parking bay.
- Completed underground electrical and traffic work at March and Spring intersections.
- Spring to Brock (north side)
- Installed new hydrant mid-block on July 23rd.
- Completed catch basins within the Brock intersection.
- Worked on installing formwork for new sidewalk.
- Commenced with underground electrical and traffic work at Brock intersection.
- Pour concrete curbs.
- Spring to Brock (north side)
- Complete formwork for new sidewalk in preparation for concrete pour.
- Pour new concrete sidewalk.
- Replace existing hydrant on east side of Brock (scheduled for July 29 – rescheduled from last week).
- Install new electrical/traffic duct across Brock, north of Queen.
- Following discussions with some of the impacted business owners, the water outage planned for last Thursday has been rescheduled for Monday, July 29 between 4:00 p.m. and 10:00 p.m. The outage is necessary to complete hydrant replacement just east of the Brock intersection (near old RBC bank) which will impact the businesses/residences located between Brock and East. Notices were delivered last week which will be followed up with an automated phone message from the PUC.
- Brock Street between Queen and Albert will be CLOSED commencing Monday, July 29th at 6:00 a.m. for a period of three (3) days to allow for installation of underground ducts at the Queen intersection. Access to the businesses on Brock between Queen and Albert will be maintained.
- The Contractor will be continuing with work on the new concrete sidewalk between Spring to Brock this week which will require rerouting of the temporary walkway to complete concrete pours. Access will be maintained to the local businesses from temporary walkway via temporary platforms and other pedestrians walking through will be directed to the south side of Queen. Once completed, pedestrians will be diverted to new concrete sidewalk.
- During the construction process, Queen Street will be reduced to a single lane of traffic and one parking lane while the Contractor works on half of Queen Street at a time. One lane is now closed between March and Brock Street on north side.
- Once the hard surfaces (such as concrete & unit pavers) are removed, temporary walkways will be established to allow access to the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and provide alternative access whenever feasible.
- Queen Street from Elgin to March will be fully closed for a period of six weeks commencing as of August 26, 2024. Additionally, there may be occasional short-term closures of Queen Street its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during the completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side.
- The work between March and Elgin is scheduled to commence mid August with closure of Queen scheduled to commence as of August 26, 2024 for 6-weeks.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025, depending upon the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
- While we understand that the construction may cause some inconvenience to the adjacent business and property owners, every effort will be made to minimize the disruptions where possible.
Queen Street Improvements: July 26, 2024
Queen Street Improvements: July 23, 2024
Queen Street Improvements: July 22, 2024
- Worked on electrical handholes & ducts for new street lighting.
- Completed grading for sidewalk and boulevard.
- Installed formwork for new sidewalk in preparation for concrete pour.
- Relocated temporary walkway and installed temporary platforms to access businesses.
- Completed catch basin, storm leads and drains.
- Worked on grading for sidewalk and boulevard.
- Excavated for new hydrant just east of Brock.
Proposed Activities
- Pour new concrete sidewalk commencing on Monday.
- Divert pedestrians to new concrete sidewalk following curing.
- Complete installation of electrical handholes at intersections.
- Complete grading for new sidewalk.
- Install formwork for new sidewalk in preparation for concrete pour.
- Pour new sidewalk later in week if timing permits or early the following week.
- Replace existing hydrant mid-block as directed by the PUC (scheduled for July 23).
- Replace existing hydrant on east side of Brock (scheduled for July 25).
Impacts
- The 1st outage is planned for Tuesday, July 23rd to complete hydrant replacement in the area of the CIBC bank. This outage will impact the businesses/residences located between Spring and Brock. PUC delivered notices last Friday which will also include an automated phone message.
- The 2nd outage is planned for Thursday, July 25th to complete hydrant replacement just east of the Brock intersection (near old RBC bank). This outage will impact the businesses/residences located between Brock and East. PUC will be delivering notices today which will also include an automated phone message.
- The Contractor will be continuing with work on the new concrete sidewalk between March and Spring and then Spring to Brock this week which will require rerouting of the temporary walkway to complete concrete pours. Access will be maintained to the local businesses from temporary walkway via temporary platforms and other pedestrians walking through will be directed to the south side of Queen. Once completed, pedestrians will be diverted to new concrete sidewalk.
- During the construction process, Queen Street will be reduced to a single lane of traffic and one parking lane while the Contractor works on half of Queen Street at a time. One lane is now closed between March and Brock Street on north side.
- Once the hard surfaces (such as concrete & unit pavers) are removed, temporary walkways will be established to allow access to the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- Queen Street from Elgin to March will be fully closed for a period of six weeks commencing as of August 26, 2024. Additionally, there may be occasional short-term closures of Queen Street its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side.
- The work between March and Elgin is scheduled to commence mid August with closure of Queen scheduled to commence as of August 26, 2024 for 6-weeks.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
Queen Street Improvements: July 17, 2024
Beginning Wednesday, July 17 at 7:00AM crews will begin installing the sidewalk form on the “Work” side of the construction fencing – This will not effect access.
Queen Street Improvements: July 16, 2024
Pouring Of Concrete Sidewalk Between March St and Spring St:
Queen Street Improvements: July 15, 2024
- Completed electrical ducts for new street lighting between intersections.
- Completed installation of new valves and decommissioning of old service on existing watermain on Monday, July 8th during planned outage.
- Completed installation of new water service on Tuesday, July 9th and Wednesday 10th during closure of Queen Street.
- Installed catch basin and storm leads.
Proposed Activities
- Complete installation of electrical handholes at intersections.
- Complete grading for new sidewalk and boulevard area commencing July 15th.
- Complete forming of new sidewalk and pour new concrete sidewalk if timing permits.
- Complete installation of catch basins and storm leads at Spring and at Brock.
- Install storm drains for new raised planters.
Impacts
- The Contractor will be working on the preparation for the new concrete sidewalk between March and Spring this week which will require short-term closures of the sidewalk at isolated locations. The Contractor will be maintaining access to the local businesses with access from March or Spring and will be directing other pedestrians walking through to the south side of Queen.
- During the construction process, Queen Street will be reduced to a single lane of traffic and one parking lane while the Contractor works on half of Queen Street at a time. One lane is now closed between March and Brock Street on north side.
- Once the hard surfaces (such as concrete & unit pavers) are removed, temporary walkways will be established to allow access to the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- Queen Street from Elgin to March will be fully closed for a period of six weeks commencing mid-August. Additionally, there may be occasional short-term closures of Queen Street its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side.
- The work between March and Elgin is tentatively scheduled to commence early August with the 6-week closure of Queen tentatively scheduled for mid to later August.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
Queen Street Improvements: July 10, 2024
Queen Street Improvements: July 9, 2024
Queen Street Improvements: July 8, 2024
- Worked on electrical ducts for new street lighting.
- Installed catch basin and storm leads.
- Replaced existing faulty water curb boxes.
- Excavated existing watermain at 3 locations in preparation for work planned for Monday, July 8th
- Erected advance notice signage for planned Queen Street closure on Tuesday, July 9th and Wednesday, July 10th.
- Complete electrical ducts for new street lighting.
- Prepare for concrete sidewalk.
- Continue with installation of catch basins and storm leads.
- Replace existing faulty water curb boxes.
- Complete new valve installations and decommissioning of old service on existing watermain on Monday, July 8th during planned outage.
- Complete installation of new water service on Tuesday, July 9th and Wednesday 10th during closure of Queen Street.
- During the construction process, Queen Street will be reduced to a single lane of traffic and one parking lane while the Contractor works on half of Queen Street at a time. One lane is now closed between March and Brock Street on north side.
- Once the hard surfaces (such as concrete & unit pavers) are removed, temporary walkways will be established to allow access to the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- Queen Street from Elgin to March will be fully closed for a period of six weeks commencing mid-August. Additionally, there may be occasional short-term closures of Queen Street its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side and working back towards March Street.
- The work between March and Elgin is tentatively scheduled to commence early August with the 6-week closure of Queen tentatively scheduled for mid to later August.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
Queen Street Improvements: July 5, 2024
Queen Street Improvements: July 2, 2024
- Completed installation of soil cells.
- Completed installation of catch basins up to Spring.
- Removed roadway asphalt.
- Completed construction of temporary walkway and erection of fencing.
- Completed removal of unit pavers and concrete curb.
Proposed Activities
- Install electrical ducts for new street lighting.
- Prepare for concrete sidewalk.
- Continue with removals of curbs and asphalt.
- Install catch basins and storm leads.
- Replace existing faulty water curb boxes.
- Prepare for Queen Street closure on Tuesday, July 9th including erection of advance notice signage.
- Excavate existing watermain in preparation for work planned for Monday, July 8th.
- Queen Street will be CLOSED to traffic commencing on Tuesday, July 9th for 2 days to allow installation of a new water service across Queen Street.
- There is a planned water OUTAGE for Monday, July 8th between the hours of 8:00 a.m. and 4:00 p.m. for the businesses/residents located on Queen between Spring and Brock. The outage is necessary to complete some upgrades to the existing water distribution system as part of the Queen Street project. Notices will be delivered by PUC to impacted businesses/residents advising of outage.
- During the construction process, Queen Street will be reduced to a single lane of traffic and one parking lane while the Contractor works on half of Queen Street at a time. One lane is now closed between March and Brock Street on north side.
- Once the hard surfaces (such as concrete & unit pavers) are removed, temporary walkways will be established to allow access to the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- Queen Street from Elgin to March will be fully closed for a period of six weeks commencing mid-August. Additionally, there may be occasional short-term closures of Queen Street its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages. There are no planned water outages for this current week.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side and working back towards March Street.
- The work between March and Elgin is tentatively scheduled to commence early August with the 6-week closure of Queen tentatively scheduled for mid to later August.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
April – June
Queen Street Improvements: June 24, 2024
- Worked on installation of soil cells.
- Installed catch basin near March.
- Set up traffic control and extended westbound lane closure to the east side of Brock.
- Decommissioned existing street lighting.
- Commenced with removal of unit pavers and curbs.
- Constructed temporary walkway with rubber mats and erected temporary fencing within removal area.
- Complete remaining soil cell.
- Complete catch basin installations.
- Install electrical ducts for new street lighting.
- Commence with concrete sidewalk late in week it timing permits.
- Continue with removals of unit pavers, curbs, asphalt etc.
- Complete construction of temporary walkway and erection of fencing up to Brock.
Impacts
Queen Street from Elgin to March will be fully closed for a period of six weeks commencing mid-August. Additionally, there may be occasional short-term closures of Queen Street its side streets. Advance notification will be provided for any closures.
Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages. There are no planned water outages for this week.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side and working back towards March Street.
- The work between March and Elgin is tentatively scheduled to commence early August with the 6-week closure of Queen tentatively scheduled mid August.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
Queen Street Improvements: June 20, 2024
Queen Street Improvements: June 17 -21, 2024
This week the Contractor is proposing to undertake the following activities between March and Spring:
- Continue work on soil cells and catch basin installations.
- Set up traffic control and close westbound lane to east side of Brock (Monday).
- Construct temporary walkway within removal area and erect fencing along walkway for access to businesses.
- City Transit to remove signs, pay & display units & bus shelter within construction area.
- Decommission and remove existing street lights (Tuesday).
- Commence with removals (i.e. curb, asphalt, unit pavers etc.) later in the week.
Impacts
- During the construction process, Queen Street will be reduced to a single lane of traffic and one parking lane while the Contractor works on half of Queen Street at a time. One lane is now closed between March and Spring Street on north side.
- Once the hard surfaces (such as concrete & unit pavers) are removed, temporary walkways will be established to allow access to the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine best timing and the provide alternative access whenever feasible.
- Queen Street from Elgin to March will be fully closed for a period of six weeks commencing mid-August. Additionally, there may be occasional short-term closures of Queen Street its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages. There are no planned water outages for this week.
- The work on Queen Street between Elgin Street and Brock Street commenced from March Street and will continue towards Brock Street along the north side before diverting to south side and working back towards March Street.
- The work between March and Elgin is tentatively scheduled to commence early August with the 6-week closure of Queen tentatively scheduled mid August.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon on the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
Queen Street Improvements: June 10 -14, 2024
Progress
During the last week, the Contractor has completed the following activities between March and Spring.
Completed removals of unit pavers, concrete curb, and asphalt along the north side of Queen.
- Constructed a temporary walkway for access to the businesses and erected fencing around the construction area and along the temporary walkway.
- Completed exploratory work to confirm the location of existing utilities.
- Decommissioned and removed existing street lights on the north side.
Proposed Activities
This week the Contractor is proposing to undertake the following activities between March and Spring:
- Install a new fire hydrant on June 11 north side near Civic 496 (Note, the work will require a water outage as outlined below).
- Commence with excavation and installation of underground soil cells upon delivery of materials.
- Install new catch basins upon delivery of materials.
Impacts
- During the construction process, Queen Street will be reduced to a single lane of traffic and one parking lane while the Contractor works on half of Queen Street at a time. One lane is now closed between March and Spring Street on the north side.
- Once the hard surfaces (such as concrete & unit pavers) are removed, temporary walkways will be established to allow access to the businesses. If there’s a need to close a walkway, the Contractor will coordinate with the businesses to determine the best timing and provide alternative access whenever feasible.
- Queen Street from Elgin to March will be fully closed for a period of six weeks commencing mid-August. Additionally, there may be occasional short-term closures of Queen Street its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during the completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages.
Schedule
- The installation of the new hydrant scheduled for Tuesday, June 11 will require a shut-down of the existing water main between March and Spring to complete the connection. The outage which will extend much of the day and will impact the businesses/residences between March and Spring who were issued Notices last week by PUC.
- The work on Queen Street between Elgin Street and Brock Street will commence from March Street and continue towards Brock Street along the north side before diverting to the south side and working back towards March Street.
- The work between March and Elgin is tentatively scheduled to commence in early August with the 6-week closure of Queen tentatively scheduled mid August.
- The work is scheduled to be Substantially completed late this fall with some work extending into 2025 depending upon the final project limits.
- The Contractor’s progress and schedule will be monitored closely.
Queen Street Improvements: June 3 to 7, 2024
- Mobilized to the site and set up a construction yard on Bay Street.
- Set up traffic control and closed the westbound lane on the north side between March Street and east of Spring Street.
- Removed traffic signals at the Queen-Spring Street intersection and installed all-way stop signs
- City Transit removed signs, pay, and display units within the construction area.
- Removals of unit pavers, curb, and asphalt on the north side.
- Temporary walkway and fencing along the walkway for access to businesses.
- Removal of street light poles on the north side within the construction area (street lighting to remain operational on the south side).
- Exploratory work to confirm the location of existing utilities.
- Queen Street will be reduced to a single lane of traffic and one parking lane while the Contractor works on half of Queen Street at a time. One lane is closed between March Street and Spring Street on the north side.
- Queen Street from Elgin Street to March Street will be fully closed for a period of six weeks commencing mid-August. Additionally, there may be occasional short-term closures of Queen Street and side streets. Advance notification will be provided for any closures.
- The work on Queen Street between Elgin Street and Brock Street will commence from March Street and continue towards Brock Street along the north side before diverting to south side and working back towards March Street.
- The work between March and Elgin is tentatively scheduled to commence early August with the 6-week closure of Queen scheduled mid August.
- The work is scheduled to be substantially completed late fall with some work extending into 2025 depending upon on the final project limits.
Queen Street Improvements: May 27, 2024
- Continuing with pre-construction building survey
- Ordering and acquiring materials
- Mobilizing equipment and manpower to the site
- Setting up traffic control for the initial phase that includes closing off the north through & parking lane between March and east of Spring street
- Commencing with removals (i.e. street lighting poles).
- Queen Street from Elgin to March will be closed for six weeks, starting mid-August. Additionally, there may be occasional short-term closures of Queen Street and its side streets. Advance notification will be provided for any closures.
- Scheduled short-term outages of the water supply may occur during completion of upgrades to the water distribution system. Advance notice will be given before any work-related outages.
Queen Street Improvements: May 23, 2024
- Beginning Monday, May 27, 2024, Queen Street will be reduced to one lane between Spring Street and March Street to accommodate construction.
- While the lane reduction is in effect, the sidewalk on the north side of Queen Street will remain open for patrons visiting local businesses. Those needing access beyond this block should use the sidewalk on the South side.
- Traffic signals at the intersection of Spring Street and Queen Street will be removed and replaced with stop signs. These signals will not be reinstalled. Instead, a pedestrian crossover (PXO) with stop control on Spring Street will be constructed on Queen Street.
- Transit users should note that the bus stop located just east of Spring Street will be temporarily removed. Other bus stops on Queen Street will be available.
Queen Street Improvements: May 8, 2024
- The improvements include replacing the asphalt roadway surface, curbs, boulevard, sidewalk, street lighting, and portions of the stormwater collection system along with the streetscape amenities such as landscaping and furnishings.
- Work on the site will begin the week of May 27, 2024. Substantial completion is expected by late fall 2024 with some work extending into 2025 depending on final project limits.
- Walkways along Queen Street may become inaccessible. The Contractor has been directed to minimize the duration of any closures and to collaborate with the business owners to provide alternative temporary access, where possible.
- Queen Street and area business and property owners, together with tenants, are invited to attend a Public Open House on Thursday, Mav 23 from 4 to 6 p.m. at the Civic Centre in the Russ Ramsay Room.
Queen Street Improvements: April 29, 2024
- Avery Construction Limited has been awarded the contract for this project.
- To meet the $6M budget allocated by Council, the current project limits are from Elgin Street to Brock Street.
- The City has applied for additional funds through the NOHFC and if successful, the project limits will be extended to Elgin Street to East Street.
- Underground services including sanitary sewers and watermains will be replaced between Elgin Street and March Street. This work will necessitate a full closure of Queen between Elgin and March for six (6) weeks.
- Queen Street will be reduced to one lane of traffic and one parking lane. There will also be short-term intermittent closures of Queen and side streets. The Contactor will provide advance notification for any closures, including signage. The businesses and the public will also be notified through media releases.